What Preparations need we do when Commission Huawei MA5800?

Postby jorna » Wed Apr 12, 2017 10:21 pm

Checking Hardware
This topic describes how to prepare the hardware required before the commissioning. This
facilitates the subsequent commissioning.
Context
Power supply and grounding
Ensure that the power cable and the grounding meet the following requirements:
The power cable and the ground cable are connected properly and are in good contact.
The labels of the power cable, ground cable, and power distribution switch are correct, legible and complete.
The connectors of the external ground cables and protection ground cables of the cabinet are connected properly, without any damage.
The power supply for the device is in the normal state.
Cables and connectors
Check the local maintenance serial port cable, network cable, optical fiber, subscriber cable, and connectors, and ensure that they meet the following requirements:
The connectors are tight and firm.
The cable jacket is intact.
Cable labels are legible.
Cables are bundled properly.
Upper-layer device
Ensure that the upper-layer device meets the following requirements:
The position of the interconnection port of the upper-layer device is correct.
The upper-layer device works in the normal state and can be used for the commissioning.
Board (daughter board)
The board (daughter board) selected should meet the
requirements for the external ports.
NOTE
Different boards (daughter boards) provide different external ports.
For details about the boards and their external ports on Huawei MA5800, see Board Overview of the MA5800 Hardware Description.
During the system startup, you are not allowed to install or remove any boards.
Preparing Tools
Cables, Maintenance terminal, Auxiliary device and meter.
Planning Data
Hardware configuration:
This includes but is not limited to the following:
Types and slot distribution of the control board and service boards-Huawei GPSF, GPHF
Types and physical positions of the upstream ports and the service ports
Networking and data plan:
This includes but is not limited to the following:
Networking mode
IP address assignment
VLAN planning
jorna
Cisco 1760
 
Posts: 102
Joined: Tue Jul 07, 2015 1:23 am

Advertisement


  • Advertisement


Similar topics


Return to Network Management

Who is online

Users browsing this forum: No registered users and 1 guest